Arbitration History

Updated  6/26/03

Arbitration Date

Project

Claim Type

Demand Amount

Award Amount

Arbitration Fee

03/19/87

830916

Improper Instructions from Inspector

$645,094

$178,827

$12,509

01/20/95

940151

Plan Ambiguity

$28,648

$17,000

$1,000

05/09/95

880017

Delay, Inefficiency, Home Office Overhead

$589,470

$555,050

$20,000

12/20/95

908005

Home Office Overhead

$419,522

$283,222

$13,130

03/27/96

931032

Plan Ambiguity

$23,151

$11,386

$1,000

05/31/96

930170

Plan Ambiguity

$162,000

$76,000

$1,600

09/06/96

940683

Delay costs, Inefficiency, Home Office Overhead, Ordered Schedule Change, Railroad Interference

$582,927

$358,582

$44,472

01/08/98

960217

OSHA compliance bridge repair

$101,226

$41,507

$1,200

02/16/98

970290

Rock hardness changed condition

$139,522

$69,761

$6,430

11/18/98

930758

Delay costs, Utility

$395,721

$143,510

$31,447

01/13/99

940613

Improper Inspection

$1,252,001

$318,212

$18,393

03/25/99

950042

Utility delay, loss of productivity, home office overhead, cost savings due to plan change

$759,519

$262,853

$11,592

09/12/00

003008

Design - Build Scope of Work

*

*

$5,166

03/14/01

970139

Plan ambiguity - payment of pipe removals

$111,414

$ 0

$1,740

07/10/01

003012

Design - Build Scope of Work

$500,000

$ 0 

$5,357

 

 

Total:

$5,710,214

$2,315,910

$175,038

* - Entitlement to design work as bid, found in favor of Contractor

Arbitration Decisions:

15

Claims now under Arbitration:

0

Portion of Demand Awarded:

38%